Construction of the Ring Road: MAG SARL Applsuded


A report published by the Ministry of Public Works has  catapulted MAG SARL, the company working on the stretch of the Ring Road from Ndu through Binka to Nkambe.  C
According to the report, physical progress of works stands at 62.32% as of May 12, 2025, earthworks, for their part, have been completed over the entire section and the company has begun laying the bituminous-bound graded aggregate base. All the box culverts have been constructed, and MAG SARL, the company in charge, intends to step up works.

As of 12 May 2025, with regard to the progress of construction works on the Ndu-Nkambe section, 31 km, it should be noted that the completion of earthworks has enabled the company to concentrate on pavements along the road. To this end, 13.115 km of earthworks have been completed, 8.710 km of sub-base have been laid and the company has begun laying the bituminous-bound graded aggregate base. The overall pavement works progress is estimated at 16.56%. Works on the ground, precisely pavement works, were marked by the laying of the improved formation from Kilometre Point 68+900 to Kilometre Point 70+000 and 0/31.5 sub-base works from Kilometre Point 63+700 to Kilometre Point 64+000. While the production and installation of 2x3 box culverts has been completed, drainage works  are ongoing with the prefabrication of 8,081 slab elements (4,040 LM), 5,375 60x60 gutter elements (10,750 LM), the installation of 60x60 gutters (9,850 LM) and the installation of kerbs, among other things. 
The first aggregate was placed in Nkambe on May 17, 2025. Donga Mantung SDO and entourage flanked by the mayor made a surprising visit to salute the ingenuity of MAG SARL team for their savvy sassy results














When News Breaks Out, We Break In. (The 2014 Bloggies Finalist)

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.