Ring Road: Work in Progress Between Nkambe- Misaje stretch









With a physical realization rate of 40.82%, construction works on the Nkambe–Misaje section of the Ring road are making some progress. The BOFAS / SUPER CONFORT Joint Venture, responsible for executing the works, has begun constructing several hydraulic structures and two bridges, while also carrying out drainage and sanitation works under the technical supervision of the CAEM / AFRICA ENGINEERING / GIC MALI Joint Venture.
The contractor, which has been granted a 6.5-month extension to the project deadline, is stepping up its efforts. 
As of November 9, 2026, site clearance activities, including cleaning and topsoil removal, have advanced. Earthworks are also progressing, with a completion rate of 80.39% recorded to date.
Of the 36 culverts scheduled for construction along the entire route, 25 have been completed and two are currently under construction.
Construction of the Misaje and Kiddung bridges is ongoing, with a completion rate of 42.66%.
The contractor has also commenced drainage works, particularly the prefabrication and installation of drainage channels, concrete-lined ditches and kerbs.
However, road pavement works are experiencing significant delays, with only the sub-base and base layers having been initiated.
Among the challenges affecting project implementation, the contractor cites difficulties in procuring fuel, cement and other construction materials, which are negatively impacting productivity. 
(Courtesy Ministry of Public Works ) Ministère des Travaux Publics du Cameroun
#everyonefollowers #everyone #everyoneactive #everyonefollowershighlights #everyone #foryouシpage #fypviralシ

When News Breaks Out, We Break In.

No comments:

Ordination ceremony of CBC Pastor Pull Crowd

GRACE BAPTIST CHURCH, NKAMBE Rev. Pastor Njoya Ghislain has officially been ordained and appointed to take over as the preacher and spiritua...